Project Updates

CSO Main Spine Tunnel

All three shafts at the Main Spine Tunnel construction site (off Allens Ave. in Providence) are completed, and the tunnel boring machine (TBM) has been lowered into the main shaft. It is currently boring the 16,000 ft. long tunnel. Work on the pump station cavern, a 68' x 68' x 100' room 250-ft below ground, is ongoing. Work continues at the site 24 hours a day, 7 days a week, and the project is anticipated to be completed in early 2008.

Contract 302.06/Foundry Shaft
The termination shaft for the CSO Phase I tunnel has been fully excavated to 250 ft deep. Work on the Woonasquatucket River Interceptor adit is ongoing

Contract 302.10C OF 032
This project will capture the flow from a CSO under Charles Street and direct the wastewater into the tunnel. Work will require a street closure on Charles Street from Orms St. south approximately 1/4 mile from March 2004 until November 2005.

Contract 807D/Bucklin Point Improvements 
The Bucklin Point Wastewater Treatment Facility was built fifty years ago in 1952. It is the second largest WWTF in Rhode Island and treats an average of 24 million gallons of wastewater per day from homes and businesses in the Blackstone Valley area. The facility has not received a comprehensive update in several decades.

The Bucklin Point WWTF improvement project will address all aspects of the facility, including a new influent pumping station, screening and grit handling facilities, dry weather primary settling tanks, effluent pumping station for dry weather flows, as well as a state-of-the-art instrumentation and control system. As a part of the improvements, the facility will also put in place a fine-bubble aeration system and ultraviolet disinfection. The first improvements went on-line in the fall of 2004.
 
The contractor is J.L. Marshall. The project is proceeding ahead of schedule.

 

One Service Road, Providence RI, 02905
Phone: 401-461-8848
Fax: 401-461-6540

© 2002 Narragansett Bay Commission, NBC, Narrabay.com. All Rights Reserved.