While the NBC has been recognized nationally for its vast
environmental achievements to improve the condition of Narragansett
Bay and its contributing waterways, it still must address another
significant source of water degradation, the combined sewer overflows
(CSOs) in Providence, Pawtucket and Central Falls.
Dry Weather Flow
Wet
Weather Flow
At
the turn of the century, most urban areas across the nation built
sewer systems to carry rain water and sewage in the same pipe. This is
called a combined sewer. During dry weather conditions, the sewer
system works fine. But, during heavy rain storms, these combined flows
frequently exceed the capacity of the sewer system and overflow into
local rivers and Narragansett Bay. This is a combined sewer overflow.
Each year, the 66 CSOs in the NBC
District release an estimated 2.2 billion gallons of untreated
combined sewage into the Bay and its tributaries, namely the
Blackstone, Moshassuck, Providence, Seekonk, Woonasquatucket, and West
Rivers. CSO's pose pollution and public health risks since they
comprise residential, commercial and industrial wastes, and other
pollution washed or dumped into storm drains. These overflows carry
pollutants in the form of sewage solids, metals, oil, grease and
bacteria which can affect the health of those who swim in CSO polluted
water or eat shellfish contaminated by these materials. To protect
human health in Rhode Island, certain areas of the bay are permanently
closed to shellfishing, and over 11,000 acres are temporarily closed
for harvesting when there is more than one-half inch of rainfall. Back to Top
In March of 1993 after several years of
study, the NBC approved a comprehensive Combined Sewer Overflow Abatement
Program. The Program proposed the construction of seven underground
storage facilities and three deep rock tunnel segments at a cost of $467
million (1992 dollars). The underground storage tanks and tunnels would
contain the sewage overflows during rain events so that the stored flows
could be returned to the system for treatment after the storm.
The combined sewer overflows into the
Bay are a violation of the Federal Clean Water Act. The NBC has entered
into a consent agreement with the RIDEM to comply with the Federal Clean
Water Act in a timely manner. The RIDEM has waived non-compliance fines,
which could be as much as $25,000 per day, per violation, while the NBC
works to implement the CSO Abatement Program. The NBC received final
approval from RIDEM in July of 1994 of the Combined Sewer Overflow
Abatement Program. The NBC then began preliminary design of its "high
priority" facilities identified in the program. These preliminary
design plans were submitted to RIDEM on January 11, 1996, as required in
the consent agreement.
In April, 1994, shortly before DEM approved
the NBC program, EPA adopted a national CSO policy which allowed more
flexibility in the development of CSO control plans. This new policy
allowed plans to be developed based on water quality improvements and
offered the potential of reducing the cost of the CSO abatement program,
which was the biggest issue raised against the proposed program.
Using this new guidance, the Commission
felt it was prudent to reassess its proposed program to determine if a
less expensive program could be developed and still meet regulatory
requirements. For this reason, the NBC initiated a series of stakeholder
workshops in January, 1996 to familiarize key stakeholders with the
proposed CSO abatement plan and regulatory requirements to determine if a
reassessment was warranted. The 40+ stakeholders represented business,
environmental and governmental interests. At these meetings, the US EPA
and RI DEM gave the attendees an overview of the regulatory framework that
had led the NBC to its currently proposed CSO control plan, and explained
the new national CSO control policy of 1994 and how it could affect NBC's
CSO planning. Economic impacts of the proposed project were discussed in
great length, as well, providing attendees with projected rate impacts
associated with the NBC's CSO program and with NBC's existing operations
and capital improvements unrelated to the CSO program. The workshops also
provided an open forum for the stakeholders to share their thoughts on the
project.
On the basis of input received from the
stakeholders in June, 1996, the NBC decided to conduct a reassessment of
its CSO control program. The reassessment consisted of a review of
alternative technologies, water quality standards and goals and a review
of the economic impacts of the program.
In February 1997, 16 potential
alternatives were presented for consideration by the stakeholders. These
alternatives consisted of different mixes of technologies with costs
ranging from $68 million to $559 million and with varying water quality
improvements. A public meeting was held on April 2, 1997 to present these
options and their expected water quality improvement. There were about 25
members of the public in attendance. The major concern raised at this
meeting again was the cost of the project and its impact on ratepayers.
After much consideration and discussion, the
stakeholders narrowed the alternatives to three options for correcting the
CSO problem. The three options were: 1) the NBC's original plan of
constructing a series of underground storage tanks and tunnels
(Alternative 16); 2) constructing nineteen sedimentation/disinfection
facilities throughout the district to provide flow through treatment
(Alternative 7A); and 3) constructing six miles of underground storage
tunnels, two sedimentation/disinfection treatment facilities, one wetland
treatment system and sewer separation of 12 areas (Alternative 17). Louis
Berger and Associates, the NBC's lead design manager for the project,
conducted a detailed evaluation of the three final alternatives and
presented these findings to the stakeholders at the August 6, 1997
meeting.
At the August 13, 1997 stakeholder meeting the NBC also addressed a
number of issues which had been raised at previous meetings relative to
CSO control. In response to these issues, the NBC agreed to do the
following:
Continue with its water quality monitoring program
Conduct stormwater attenuation pilot studies
Evaluate instituting a stormwater rate structure
Evaluate a proposed CSO debt ceiling
A continuous technology reassessment
Be a stakeholder in a watershed management program managed
by
others Back to Top
Although there was a consensus that only
the first phase of the three-phased plan be designed and constructed which
should take approximately seven years, the Commission is required by law
to present a comprehensive plan to address all three phases of the
pollution control initiative. Once the first phase is complete, the
Commission is committed to a two-year hiatus to evaluate the water quality
improvement and reassess the technologies to determine if future phases of
the plan should be modified.
With this approach, a reduction in overflow
volume of approximately 40% is expected after Phase I facilities are
complete and approximately 98% after all phases are complete. Shellfishing
and bathing uses will be enhanced once the project is complete.
Alternative 17 was selected because it has the
lowest operation and maintenance cost and construction costs are about
one-third less than the originally proposed plan. The first phase of Alternative 17 is expected to cost approximately
$275 million. This plan
also results in good water quality improvement because most storm flows
are stored in the tunnel and are provided with a high level of treatment
after the storm at the NBC's two existing wastewater treatment facilities.
Due to the small number of facilities that the
NBC would have to operate, the system is very reliable and can be easily
maintained. Also, because there are only two remote facilities adding
chlorine, the toxic impacts of chlorine are minimal. In addition, permit
limits for fecal coliform bacteria can be more easily attained with this
alternative than alternative 7A.
Water quality improvements based on both sewer
system and receiving water modeling, are a reduction in overflow volume of
approximately 40% after Phase I facilities are complete and approximately
98% after all phases are complete. Untreated overflow events with the
entire plan in place are projected to be about four per year. Shellfishing
and bathing uses will be greatly enhanced once the project is complete. It
is projected that areas that are now conditionally closed to shellfishing
will be closed 50% less in the Upper Bay and 78% less is the lower Bay
after Phase I of the project is completed. These numbers will increase to
68% and 95% less, respectively, after all facilities are in place. Back to Top
The NBC held a public hearing on the draft CSO
Concept Design Report (CDR) Amendment in January 1998 and submitted the
final CDR Amendment to DEM on April 17, 1998. On May 19, 1999, the RI DEM
held a public hearing on its intent to issue a Finding of No Significant
Impact (FONSI) for Alternative 17, and accepted public testimony in favor
of and opposed to the NBC's CSO Plan. On July 12, 1999, RI DEM issued the
FONSI. "This plan reflects many years of hard, thoughtful work on the
part of professionals and stakeholders who undertook a careful examination
of the very complex and challenging CSO abatement issue," said DEM
Director Jan H. Reitsma. "There has been an extensive evaluation of
environmental benefits and impacts, as well as alternatives, which
indicate that the proposed project will be the most environmentally sound,
as well as cost-effective, means to control CSO discharges. Given the long
history of planning and evaluation and the quality of analysis to date,
DEM strongly believes it is time to move forward and to implement improvements and
clean up the urban rivers around Providence."
Reitsma also note the importance of the
stakeholder process ion helping to steer the project in a direction that proved
to be financially and socially acceptable, as well as
environmentally sound. "Public involvement was a key factor
throughout the entire CSO evaluation process, as well it should be for a
project of this size, scope, and cost," said Reitsma. "I commend
the NBC for seeking public input and using this input as guidance in
choosing the recommended alternative."
With
approval of the final plans and specifications received from RI DEM in
2001, the NBC began construction on the first of ten construction
contracts in Phase I in June 2001, and awarded the contract for the
largest construction contract in Phase I, the Main Spine Tunnel, in
September 2001. Construction on the MST is began in the
spring of 2002. Back to Top